Flooding at a substation in the Pretoria CBD led to a power outage which impacted essential institutions such as the Pretoria Magistrates Court and the police station. But what caused the flooding remains a mystery.

“Power was finally restored just after 11AM on Tuesday morning after technicians successfully drained out the water from flooded substation,” said Tshwane spokesperson Selby Bokaba.

The substation, which is housed at the basement of the Gauteng Provincial Government building in the Pretoria CBD, was somehow filled with water, resulting in a power outage at essential entities.

ALSO READ: City of Tshwane blames sabotage for 5-day power outage in Laudium

COURT AND POLICE STATION EXPERIENCE OUTAGE

The Pretoria Magistrates Court and the Pretoria Central Police Station are among those that were affected by the outage on Monday.

This includes the National Department of Social Development, the Department of Land Affairs and Rural Development and the Gauteng Provincial Government building consumers.

According to DA Gauteng Shadow MEC for Community Safety Crezane Bosch, suspects were turned away due to the court’s outage.

“These suspects were supposed to have appeared in court [on Monday] morning but were turned away due to an alleged outage at the court due to a sub-station that was flooded…” she said.

But the court used generators in the interim, said National Prosecuting Authority (NPA) regional spokesperson Lumka Mahanjana.

“NPA adjourned all criminal cases on the roll in absentia and bail applications were dealt with at the Court 62 in Kgosi Mampuru Correctional Services. Electricity has since been back and the courts are back to its normal operation.”

FLOODING REMAINS A MYSTERY

The flooding of the substation started last Wednesday. The initial water level was 2 300 millilitres and sat at 300 millilitres on Tuesday.

Water seeped into the switch gears, requiring technicians to replace oil as a precautionary measure.

ALSO READ: WATCH: Flooding in parts of Tshwane – rescue efforts underway

“Technicians managed to successfully drain out water, cleaned and dried out the panels to the substation that was flooded… and the cause of the flooding is not yet known.

“The City appreciates the consumer’s patience during that period of an unforeseen interruption,” Bokaba said.

[email protected]





Flooding at a substation in the Pretoria CBD led to a power outage which impacted essential institutions such as the Pretoria Magistrates Court and the police station. But what caused the flooding remains a mystery.

“Power was finally restored just after 11AM on Tuesday morning after technicians successfully drained out the water from flooded substation,” said Tshwane spokesperson Selby Bokaba.

The substation, which is housed at the basement of the Gauteng Provincial Government building in the Pretoria CBD, was somehow filled with water, resulting in a power outage at essential entities.

ALSO READ: City of Tshwane blames sabotage for 5-day power outage in Laudium

COURT AND POLICE STATION EXPERIENCE OUTAGE

The Pretoria Magistrates Court and the Pretoria Central Police Station are among those that were affected by the outage on Monday.

This includes the National Department of Social Development, the Department of Land Affairs and Rural Development and the Gauteng Provincial Government building consumers.

According to DA Gauteng Shadow MEC for Community Safety Crezane Bosch, suspects were turned away due to the court’s outage.

“These suspects were supposed to have appeared in court [on Monday] morning but were turned away due to an alleged outage at the court due to a sub-station that was flooded…” she said.

But the court used generators in the interim, said National Prosecuting Authority (NPA) regional spokesperson Lumka Mahanjana.

“NPA adjourned all criminal cases on the roll in absentia and bail applications were dealt with at the Court 62 in Kgosi Mampuru Correctional Services. Electricity has since been back and the courts are back to its normal operation.”

FLOODING REMAINS A MYSTERY

The flooding of the substation started last Wednesday. The initial water level was 2 300 millilitres and sat at 300 millilitres on Tuesday.

Water seeped into the switch gears, requiring technicians to replace oil as a precautionary measure.

ALSO READ: WATCH: Flooding in parts of Tshwane – rescue efforts underway

“Technicians managed to successfully drain out water, cleaned and dried out the panels to the substation that was flooded… and the cause of the flooding is not yet known.

“The City appreciates the consumer’s patience during that period of an unforeseen interruption,” Bokaba said.

[email protected]

FOLLOW US ON GOOGLE NEWS

Read original article here

Denial of responsibility! Quick Telecast is an automatic aggregator of the all world’s media. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials, please contact us by email – [email protected]. The content will be deleted within 24 hours.

Leave a comment
Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

buy kamagra buy kamagra online